APPENDIX C

Planning Procedure

Purpose

The objective of the CM planning procedure is to develop required guidance for the deployment of the configuration management procedures. This procedure involves the identification of the project configuration controller, developing the CM plan and ensuring its integration with the overall project plan.

Definitions

No

Term

Definition

1

Configuration Item (CI)

An aggregation of work products that is designated for configuration management and treated as a single entity in the configuration management process.

2

Baseline

The configuration information formally designated at a specific time during a product's or product component's life. Configuration baselines, plus approved changes from those baselines, constitute the current configuration information. Usually, the baseline term describes how different CIs are related to each other and how this CIs are related to project’s milestones.

3

Configuration Management Audit

An audit conducted to verify that a configuration item conforms to a specified standard or requirement.

Entry Criteria (OR)

No

Criteria

Exit Criteria Of

1

Candidate Requirements Approval

RITSOL_PD_Requirements_Elicitation_Procedure

2

Rework from project plan finalization

RITSOL_PM_Finalize_Project_Plan_Procedure

Inputs

No

Input

Coming from/Output Of

1

Approved Candidate Requirements

RITSOL_PD_Requirements_Elicitation_Procedure

2

Approved Partial PMP

RITSOL_PM_Initiation_Procedure

Activities

No

Activity

Responsible

Input

Output

Temp/Form

1

Identify a Configuration Controller (CC).

PM

Approved Partial PMP

Identified CC

 

2

Determine the CM organization and structures.

PM and CC

Approved Partial PMP

Identified Organization and Structure

RITSOL_CM_ Configuration_ Management_ Plan_Template

3

Determine the configuration control board.

PM and CC

Identified Organization and Structure

Indemnified CCB

RITSOL_CM_ Configuration_ Management_ Plan_Template

4

Determine roles and responsibilities.

PM and CC

Identified Organization and Structure

Identified Roles and Responsibilities

RITSOL_CM_ Configuration_ Management_ Plan_Template

5

Determine training needs.

PM

Identified Roles and Responsibilities and CCB

Identified Training Needs

RITSOL_CM_ Configuration_ Management_ Plan_Template

6

Determine and describe the detailed CM environment.

CC

Approved Partial PMP

Identified CM Environment

RITSOL_CM_ Configuration_ Management_ Plan_Template

7

Determine the required non-human resources.

PM and CC

Identified CM Environment

Identified Non-Human Resources

RITSOL_CM_ Configuration_ Management_ Plan_Template

8

Determine the detailed project repository structure.

CC

Approved Partial PMP

Identified Project and Responsibility Structure

RITSOL_CM_ Configuration_ Management_ Plan_Template

9

Determine the configuration items.

CC

Identified Project and Responsibly Structure

Identified Initial CIs List

RITSOL_CM_CIs_List_Form

10

Determine the naming conventions.

CC

Approved Partial PMP

Identified Naming Conventions

RITSOL_CM_ Configuration_ Management_ Plan_Template

11

Determine the types of baselines during the project and baselining criteria.

PM and CC

Approved Partial Plan

Identified Baselines types and Criteria

RITSOL_CM_ Configuration_ Management_ Plan_Template

12

Determine the relation between project milestones and major baselines.

PM and CC

Identified Baselines types

Identified Major baselines

RITSOL_CM_ Configuration_ Management_ Plan_Template

13

Determine the change management evaluation mechanism.

PM and CC

Approved Partial PMP

Identified Evaluation Mechanism

RITSOL_CM_ Configuration_ Management_ Plan_Template

14

Determine the change decision taking mechanism.

PM and CC

Approved Partial PMP

Identified Decision Mechanism

RITSOL_CM_ Configuration_ Management_ Plan_Template

15

Determine the types of the CM audits that will be conducted in the project.

PM and CC

Approved Partial PMP

Identified Audits Types

RITSOL_CM_ Configuration_ Management_ Plan_Template

16

Determine the relation between the baselines and CM audits.

CC

Identified Audits Types

Identified Relations

RITSOL_CM_ Configuration_ Management_ Plan_Template

17

Determine the reporting mechanism and frequency.

CC

Approved Partial PMP

Identified Reporting Mechanism

RITSOL_CM_ Configuration_ Management_ Plan_Template

18

Determine the data to be under the data management plan.

PM and CC

Approved Partial PMP

Identified Data

RITSOL_CM_ Configuration_ Management_ Plan_Template

19

Determine the access control permissions.

CC

Identified Data

Identified Permissions

RITSOL_CM_ Configuration_ Management_ Plan_Template

20

Determine data retention rules.

PM and CC

Identified Data

Identified Retention

RITSOL_CM_ Configuration_ Management_ Plan_Template

21

Determine backups and recovery policies, data and plan.

PM and CC

Identified Data

Identified Backups and Recovery Plan

RITSOL_CM_ Configuration_ Management_ Plan_Template

22

Consolidate and finalize the CM plan.

CC

Identified CIs

Initial CM Plan

RITSOL_CM_ Configuration_ Management_ Plan_Template

23

Review the initial CM plan.

PM

Initial CM Plan

Updated CM Plan

 

24

Add outputs to the CM repository.

PM

Updated CM Plan

Stored CM Plan

 

25

Collect measurements as per the identified metrics below.

PM

Stored CM Plan

Measurements

 

26

Monitor the progress.

PM

Measurement

Deviations

 

27

Approve the outputs of the procedure.

PM

Updated CM Plan and CIs List

Approved CM Plan and CIs List

 

Outputs

No

Output

Going To/Input Of

1

Approved Configuration Management Plan

RITSOL_PM_Estimatation_Procedure

RITSOL_CM_ Configuration Audit Checklist

RITSOL_CM_Maintaining_CM_Environment_Procedure

RITSOL_PM_Risk_Planning_Procedure

2

Approved CIs List

RITSOL_PM_Estimatation_Procedure

RITSOL_CM_ Configuration Audit Checklist

RITSOL_CM_Maintaining_CM_Environment_Procedure

RITSOL_PM_Risk_Planning_Procedure

Exit Criteria (AND)

No

Criteria

Entry Criteria Of

1

Configuration Management Plan Approval

RITSOL_PM_Estimatation_Procedure

RITSOL_CM_ Configuration Audit Checklist

RITSOL_CM_Maintaining_CM_Environment_Procedure

2

CIs List Approval

RITSOL_PM_Estimatation_Procedure

RITSOL_CM_ Configuration Audit Checklist

RITSOL_CM_Maintaining_CM_Environment_Procedure

Metrics

These measures can be useful to support the process enactment, or future enactments.

·         Actual versus planned time and effort.

·         Number of CIs.

Subjects for Review

·         Configuration Management Plan (as a part of PMP)

·         CIs list (as a part of PMP)

Records

·         None

Configurable Items        

·         Configuration Management Plan

·         CIs list

 

 

Quality Management System (QMS)